Concrete Balancing Tank

A proprietary panel formwork system was used to construct the 3000 mm high circular walls and deck of this water retaining structure.

 

A high standard of workmanship in the complex reinforcement, formwork and concrete placement was required to meet the exacting standards of the project engineer. A 50/50 blend of GGBS and OPC was used for all concreting works to ensure that correct curing could take place.

 

Contract: 19m diameter, 750 m³ Capacity Water Attenuation Tank, Selby

Engineer: Eastwood and Partners (Consulting Engineers) Limited

Carried out: July to December 2006

 
 

Website Navigation: Home | About Us | Projects | Contact Us

Beighton Construction Ltd | 58 Dunston Road, Chesterfield, Derbyshire, S41 8XA

Email: beighton@beighton-construction.co.uk | Phone: 01246 451098


 

 

Beighton Construction Ltd | Company number 01015616 | Registered Office: 58 Dunston Road, Chesterfield, Derbyshire, S41 8XA

Website content ©2021-2022 Beighton Construction Ltd | Website Terms

Website design by Pocket M ©2004-2022